Tuesday, November 30, 2010
Tuesday, November 23, 2010
Windows
The Pella truck with our windows arrived today, however, the three south windows were not on the truck. The kit to put together these extra large windows was not ordered...and is still back at the factory in Kentucky...It is what it is.
Posted by Dan & Karen at 8:19 PM 1 comments
Monday, November 22, 2010
Hole in the Wall
After drilling the two inch hole in the wall, Dan is digging out the foam. This is to allow access to the conduit in the wall..
Posted by Dan & Karen at 10:36 AM 0 comments
Tub/shower Unit
This tub/shower unit will be in the second bathroom. The trailer sure made transporting this unit easy.
Posted by Dan & Karen at 10:29 AM 0 comments
Friday, November 19, 2010
The Last Frame Up
Dan is leaning on the wall that was framed last. This will become part of the island in the kitchen.
Posted by Dan & Karen at 5:48 PM 0 comments
Birthday
The crew, Caesar, Alex, and Roberto, finished framing on Thursday. We celebrated Caesar's birthday before they left. Hopefully, they will return next week to put in the missing panels and the windows.
Posted by Dan & Karen at 5:40 PM 0 comments
Hole in the Roof
A pellet stove is on order and will be in the great room. The hole in the roof and the pipe and black box needed to be installed before the framing inspection.
Posted by Dan & Karen at 5:16 PM 0 comments
Wednesday, November 17, 2010
Windows
The window openings in the great room are getting a "window lift" due to panels that were made incorrectly.
Posted by Dan & Karen at 8:07 PM 0 comments
Arches
Arches, arches everywhere. Actually there are now two in the framing stage. The first one that you see is in the mud room, notice the barrel ceiling. This is where we will sit down, change our shoes & hang up our coats. The second one is in the great room.
Posted by Dan & Karen at 7:42 PM 0 comments
Tuesday, November 16, 2010
Nails
Here you see Dan removing nails from boards that were used to reinforce the framing while the trusses were installed.
Posted by Dan & Karen at 8:30 PM 0 comments
Monday, November 15, 2010
Friday, November 12, 2010
Front Gables Completed
The crew started early (7:30) and completed the front gables. They stopped at 3:00 and will return on Monday to complete the framing on the inside.
Posted by Dan & Karen at 4:27 PM 0 comments
coffee stain
Oops! The crew has been very careful about not spilling things on the floor, since we plan to stain the concrete. However, Bryon's coffee tipped over in the kitchen. Luckily it landed right next to the north wall where the cabinets will be located.
Posted by Dan & Karen at 4:10 PM 0 comments