Sunday, October 19, 2008

Floating the Cement

Cement Pad


Cement Pad for the 30 X 40 metal building.

Set Up






The bolts, nuts, and tools are housed in these handy blue boxes. The metal pieces were placed around the cement before being erected.

First Column






Dan operated the bobcat and raised the first column while Karen guided it over the 4 anchor bolts. Next the girt was added.

Day 2


4 columns 2 girts

Center Rafters



The bobcat was used to help connect the two 250 pound rafters which will be placed on the two center columns.

Handy Ropes



Dan rigged up this rope system to help raise the East end girt.

Help




Our helpful neighbor, Curt Sorenson, is working on putting up a West end girt.

Columns Up




All 12 columns are bolted in place.

Level for Plumb Line



Checking for plumb.

Rope



We used a rope to align the rafter to the column while lifting the rafters.

Bobcat Helped


The bobcat aided in lifting the 500 pounds of the middle rafters. The roust about is connected to the chain in the middle. It is the yellow piece of equipment that we rented.

Roust About



We rented this roust about to help in raising the 500 pound rafters.

Rafters



Dan is putting in the bolts on the east end rafters. Notice the yellow piece of equipment that is attached to the chain on top of the rafter. We rented this "roust about" which was supposed to lift loads 15 feet. Actually it went up only about 14 ½ feet.

West End Rafters



All of the rafters are up. Here you can see 12 columns, 10 girts, 2 header, and 6 rafters. Day 5

Up and Down



Dan went up and down the scaffold and/or ladder about 8 times per purlin. Lots of exercise. But he says it probably won't help his golf game.

Cables





Detail of cable eye bolt.
8 cables were attached, four under the purlins on the east bay and 2 on the north and 2 on the south side, making an X.

Drilling



The electric drill had to be used to get those holes ready for the bolts.

Hard Hats



Hard hats are good protectors.

Overlapping



Overlapping the purlins and standing them up was tricky. 10 bolts were added to the purlins in the center attachments.