Monday, August 30, 2010
Leaks
The water system wasn't holding air - for the second time. Although it passed inspection, it developed two leaks. Hopefully this will be the last leak and we can get the slab poured later this week.
Posted by Dan & Karen at 5:27 PM 0 comments
Thursday, August 26, 2010
Radiant Floor Tubing
Two men from Ted's Plumbing & Hydronics are installing the tubing. Dan is finishing up the "fines" in the garage area.
Posted by Dan & Karen at 12:34 PM 0 comments
Tuesday, August 24, 2010
Pushing the gravel
Gus and Nancy came for a few days on their way home from Creede, CO where they were attending an RV rally. We sure enjoyed their visit and help today!
Posted by Dan & Karen at 10:19 PM 0 comments
Double rainbow
This view of the double rainbow is to the east. The garage area has about several inches of "fines" or gravel, in preparation for the radiant floor tubing.
Posted by Dan & Karen at 10:06 PM 0 comments
Cutting the Foam
We were lucky to have our friend, Curt Sorenson, help us install insulation under the slab. After Curt and Karen finished taping the insulation, Curt cut the foam for the stem walls. Dan was busy putting glue on the foam for the stem walls.
Posted by Dan & Karen at 9:54 PM 0 comments
Friday, August 20, 2010
Garage floor is "foamed"
We have put down the black plastic and the foam on the garage floor. We still need to put foam on the sides of the stem wall in the garage area.
Posted by Dan & Karen at 3:15 PM 0 comments
Thursday, August 19, 2010
Foam
The 1 1/2 " slab insulation foam was delivered this morning. Dan and I plan to install it ourselves.
Posted by Dan & Karen at 3:23 PM 1 comments
Sunday, August 15, 2010
Saturday, August 14, 2010
Sandbox
Tools needed for leveling the "sandbox" included:
the bobcat, the rakes, the shovels, the string, & the measuring stick.
Dan, using his bobcat, moved buckets of dirt into the needed areas, Karen and Mary used the shovel & rake to smooth the dirt and then the string and measuring stick to ensure the correct level. This view is to the North and we are working in "Dan's room."
Posted by Dan & Karen at 3:42 PM 0 comments
Labels: Moving dirt
Wednesday, August 11, 2010
August 10, 2010
Ted's Plumbing and Hydronics and Tony Carestia Excavating worked today on the rough-in plumbing and the septic systems. Ted has had to wait for some parts to arrive before calling for an inspection. Hopefully he'll finish up tomorrow.
Tony has worked hard on installing our septic system. He'll bring some more gravel up tomorrow to finish up the leach field and wait for the inspector.
Posted by Dan & Karen at 8:42 AM 0 comments
Tuesday, August 10, 2010
Friday, August 06, 2010
Thursday, August 05, 2010
Monday, August 02, 2010
Finished Foundation
The guys came back today and removed the forms from the stem wall. It looks really good, no voids, etc. Next up is backfilling once I get the water line stubbed in.
Posted by Dan & Karen at 1:14 PM 0 comments